Eureka Business Park and Bradford logistics
Eureka Business Park (Cleckheaton Road, BD4) at the M606 J1/M62 J26 junction is Bradford's primary modern logistics location. 500 kW – 2 MW PV potential per building on modern (2005+) profiled steel logistics units. Key operators: DPD Bradford hub, Royal Mail Bradford DO (BD2), Hermes/Evri Bradford cross-dock, mixed logistics. Northern Powergrid G99 for BD4: 5-6 months. Self-consumption parcel cross-dock: 65-72%; with EV van fleet integration: 79-87%. Payback cross-dock without EV: 6-7 years. With EV fleet: 4.5-5.5 years.
Northern Powergrid: Bradford DNO specifics
Northern Powergrid covers Bradford and West Yorkshire. G99 for BD postcodes: 5-7 months typical for 250 kW – 2 MW commercial. BD4 (Eureka/M606): 5-6 months. Bradford city centre Canal Road corridor: 5-7 months. Bradford North (BD2, BD3): 5-7 months. Shipley and Saltaire (BD18): 5-7 months. Good industrial grid capacity throughout Bradford — the legacy manufacturing infrastructure means high-capacity substations near most industrial areas. G98 (fit and inform the DNO) only covers inverters up to 16 A per phase, about 3.68 kW single-phase or 11 kW three-phase; virtually every warehouse system is above that and needs G99 approval from the DNO before installation.
Common questions
Can I still get IETF funding for warehouse solar?
No. The IETF is closed: its last application window shut on 19 April 2024, GOV.UK confirmed in July 2025 that no successor fund is planned, and solar PV was never an eligible technology.
What payback should I expect for Eureka Business Park logistics solar?
Eureka cross-dock without EV fleet: 6-7 years simple payback. Eureka logistics with EV van fleet integration (10-20 vans): 4.5-5.5 years. After 100% AIA: subtract 1-1.5 years. The EV integration is strongly recommended for all Bradford parcel hub operators to achieve viability under 6 years. OZEV Workplace Charging Scheme (£500/socket to 31 March 2027) reduces EV charge point capex further.